Continuing Studies Building lobby renovations

PURPOSE OF PROJECT

To modernize and renovate the lobby area with provision of a new registration area with support offices

WHAT WAS DONE

The existing kiosk was removed and a new structure that matched the building’s architecture was constructed. This doubled the size of the office area, therefore creating a much more student accessible counter.

 

INCEPTION TO COMPLETION

Project inception: September 2014
Project completion: February 2015

PROJECT MANAGER

Jay Jethwa

PROJECT COORDINATOR

David Kosub